Electric Gold Melting Furnace Cooling water description

This equipment water cooling is very important in this emphasis Be sure to turn on the water before heating and make sure the water supply of the equipment is normal before starting the machine.

 The function of cooling water

1. Cooling induction ring
2. Cool the internal power components and high-frequency transformers of induction heating equipment.

Requirements for cooling water

1. Inlet water temperature:<50℃
2. Pressure:>0.1MPa
3.Flowrate:5-20L/min,The highest water temperature at the outlet does not exceed 60℃
4. Water quality: clean demineralized water

Cooling water quality-important

If the water contains mud, sand, rust, fiber, hair, etc., it will seriously block the equipment cooling pipe and cause the water flow to decrease. Reduce the cooling effect, cause the internal power devices of the equipment to burn out, and the pipes to burn through, resulting in shutdown and production. High hardness water or limestone water contains a large amount of calcium and magnesium plasma, long time work, the radiator and cooling pipe inside the equipment will form a thick scale, blocking the cooling effect will also lead to the burning of internal power device equipment.

Equipment water supply pump, pool capacity reference table

Melting Equipment

gold melting furnace cooling water

Main feature

1. High power, low frequency, good air permeability。
2. High efficiency, low power consumption, simple operation, and installation。
3.100% full load, 24 hours continuous working ability。
4. All-solid-state IGBT inverter power adjustment to realize automatic frequency tracking
5. Various automatic protection functions such as overvoltage, overcurrent, overheating, etc. ensure the safety and reliability of the equipment.
6. Temperature display and setting.

Main specifications and models: TG-15A ,TG-45AB ,TG-25A ,TG-60AB ,TG-35AB

gold indution melting furnace specifications and model

Electric Gold Melting Furnace control panel

1. Power: Close the control switch, and the light is on to indicate that there is power.
2. Working: The buzzer beeps when heating.
3. Overvoltage: The device allows an input voltage of 200-420V. When the input voltage is too high, the device automatically stops heating, the overvoltage indicator light is on, and a continuous beep sounds.
4. Water shortage: The induction coil and main internal parts of the equipment are all lack of water cooling. If the water flow is too small or the cooling water temperature is too high, or the internal pipes are blocked due to the use of the machine for a long time, the water cooling effect becomes worse, the equipment will automatically stop working at this time, and the buzzer will sound.
5. Overcurrent: When this light is on, it may happen in the following situations: (1).Interference signal (2).The internal temperature is too high (3).Equipment failure The contact between the workpiece and the induction coil causes a short circuit Contact between two circles of induction coil (6). If the grid voltage is too low or the load capacity of the grid is too poor, when the above situation occurs, turn off the power and turn it on again to eliminate the alarm and then heat up. There will be several situations a.a. Everything is normal again, indicating that the contact between the workpiece and the induction coil causes the induction coil to short-circuit b. The overcurrent alarm is still under high current, and it can work under low current: indicating that the induction gap is too small, the grid voltage is too low, the load capacity of the grid is too poor, or the internal fault of the machine c. It keeps on alarm and cannot work: it means that there is contact between the two coils of the induction coil or the internal failure of the machine.
6. Heating: In an automatic or manual working state, this light is on to indicate that the heating process is in progress
7. Heat preservation: only in the automatic working state, this light is on, it means heat preservation and heating are in progress
8. Button 1. Start button: Press this button once, and the device will start heating 2. Stop button: Press this button once to stop heating
9. Thermostat 9.1 Temperature display function. Actual crucible temperature display 9.2 Heat preservation function  After the temperature is set, after the MAX is adjusted to the maximum when the temperature reaches the set temperature, MAX will not work. At this time, the machine is in a heat preservation state. When the temperature is to be heated again, the MIN knob can be adjusted to increase the temperature.

 

1. Power: Close the control switch, and the light is on to indicate that there is power.

2. Working: The buzzer beeps when heating

3. Overvoltage: The device allows an input voltage of 200-420V. When the input voltage is too high, the device automatically stops heating, the overvoltage indicator light is on, and a continuous beep sounds.

4. Water shortage: The induction coil and main internal parts of the equipment
are all lack of water cooling. If the water flow is too small or the cooling
water temperature is too high, or the internal pipes are blocked due to the
use of the machine for a long time, the water cooling effect becomes worse,
the equipment will automatically stop working at this time, and the buzzer will sound.

5. Overcurrent: When this light is on, it may happen in the following situations:
(1).Interference signal
(2).The internal temperature is too high
(3).Equipment failure
(4).The contact between the workpiece and the induction coil causes a short circuit
(5).Contact between two circles of the induction coil
(6).If the grid voltage is too low or the load capacity of the grid is too poor, when the above situation occurs, turn off the power and turn it on again to eliminate the alarm and then heat up. There will be several situations
a. Everything is normal again, indicating that the contact between the workpiece and the induction coil causes the induction coil to short-circuit
b. The overcurrent alarm is still under high current, and it can work under low current: indicating that the induction gap is too small, the grid voltage is too low, the load capacity of the grid is too poor, or the internalfault of the machine
c. It keeps on alarm and cannot work: it means that there is contact between the two coils of the induction coil or the internal failure of the machine.

6. Heating: In an automatic or manual working state, this light is on to indicate that the heating process is in progress

7. Heat preservation: only in the automatic working state, this light is on, it means heat preservation and heating are in progress

8. Button
Start button: Press this button once, and the device will start heating
Stop button: Press this button once to stop heating

9. Thermostat

9.1.Temperature display function。
Actual crucible temperature display
9.2Heat preservation function
After the temperature is set, after the MAX is adjusted to the maximum, when the temperature reaches the set temperature, MAX will not work. At this time, the machine is in a heat preservation state. When the temperature is to be heated again, the MIN knob can be adjusted to increase the temperature.

Rear panel function

Electric Gold Melting Furnace control panel

Installation:

1. Cooling water connection: (see attached page for connection diagram, waterway connection diagram)
Connect the water inlet pipe to the water inlet pipe end at the rear of the equipment, and connect the water outlet pipe to the water outlet pipe end at the rear of the equipment to ensure a good connection to prevent water leakage. The water inlet pipe can be connected to a tap or user-provided circulating water device. The inlet water should be guaranteed to have a certain pressure and flow rate to prevent equipment damage caused by insufficient pressure and water flow. The recommended water pressure is 0.05-0.2Mpa and the water flow rate is 2-5L/min. There is a water pressure switch in the equipment to effectively protect it from no pressure. If there is no water, it will automatically stop working and emit a buzzer sound. In addition, the induction coil of this equipment is soldered, which will cause the tin to melt when heated without cooling water, which can play a role in water-free protection. For the installation and use of cooling water, there are several suggestions:
a. The cooling water source should ensure a stable water supply, and it is better to use a water pump to circulate it is more reliable
b. The cooling water should be clean and non-corrosive.
c. The cooling water temperature should not be too high, preferably lower than 45℃.
d. Check that the cooling water is unobstructed before heating.
e. Do not change the induction coil soldering to brazing or silver soldering.

2. Device power connection:
According to the input power and phase number requirements of the model. It must be a fuse box, it is not allowed to directly use the air switch in the machine instead.

melting furnace wire requirement

3. Protective ground connection:

Ground the equipment with a wire of about 6mm2 to prevent electricity leakage.

Operation Steps:

1. Ensure that all required installation work has been completed.
2. Turn on the cooling water.
3. Close the external power switch, close the air switch on the back of the device, and close the power switch on the front panel.
4. Adjust the heating current adjustment knob MAX to the desired position.
5. Press the start button to start heating, at this time the buzzer beeps, and the output current display shows the heating current.
6. Press the stop button to stop heating.
7. When shutting down, turn off the front electric switch first, then turn off the external main switch, and then turn off the water.
The air switch of this equipment is mainly designed for current-limiting protection. In order to prolong its service life, it should be operated as little as possible. Therefore, it is recommended that the user must configure the device on the switchboard to control the power supply with a knife.

Precautions for use:

1. The user should meet the power supply requirements (power and cross-sectional area requirements) of the equipment according to the power consumption of the entire plant and the capacity of the power supply transformer. Do not connect the wrong power supply for single-phase 220V and three-phase 380V to avoid damage to the machine. When the grid voltage is higher than the specified range, please do not use the equipment.
2. The water quality should be kept clean for a long time. It is best to set up dust blocking facilities and clean the water tank (pool) regularly. In order to prevent long-term use, the water pipe in the machine should be cleaned regularly (usually within two months) with a descaling agent to clean the water circuit of the equipment. The specific method is: the descaling agent is an ordinary car water tank descaling agent, and the ratio is 1:40. The water circuit is cleaned for 1 hour and rinsed with clean water. The power supply of the equipment must be cut off when cleaning.
3. Connect water first, then power on. Under any circumstances, it is not allowed to operate the equipment without water.
4. The water temperature in the water tank should be kept within 17℃-50℃, the water tank should be placed in an indoor ventilated place, the pool is generally arranged the underground, and covered with dustproof, sunscreen cover. In winter, in order to prevent the equipment water pipe from freezing or blocking when it is not in use, the circulating water in the equipment should be emptied immediately after stopping the work. The specific operation method is to pull the water supply pump out of the water tank, air transport for 3 minutes, and use the air to discharge the water stored in the water pipe in the equipment.
5. In order to prevent electric shock, always check whether the grounding wire is reliable. When replacing the inductor, the water should be cut off and it can be replaced after power failure.
6. The working site environment of the equipment is generally harsh. Prevent dust, water vapor, and oil vapor from entering the machine during work. Generally, open the side door of the equipment to check the influence of dust and water vapor in the machine during a week. If there is too much dust in the machine, the water vapor will pass It is important to turn on the equipment fan to dry for a period of time when it is not working. Generally, it is enough. If the working environment is particularly bad, it is recommended to turn on the blower for ten minutes before starting work every day.
7. The equipment should be inspected and repaired by professionals.
8. This equipment is the same as all other induction heating equipment. The configuration of the inductor, such as the number of turns, height, shape, current direction, and the distance between the inductor and the heating workpiece, all affect the efficiency of induction heating. Serious improper configuration may cause the equipment to fail to start normally or damage the equipment. Therefore, changing the sensor size should be carried out by a knowledgeable professional or contact our technical department. Our factory provides free consulting services.

Equipment packing list
Portable unit type::
1. One main machine
2. One induction ring。
3. One Crucible, One clamp

gold melting furnace Fault resolution

15A melting furnace connection diagram